Pentagon trims F-35 Block 4 costs
The Pentagon is reducing the scope of F-35 Block 4 after cost growth and delays pushed completion to 2031 at the earliest, with the program now expected to cost more than $6 billion above prior estimates. The Government Accountability Office reported that Block 4 costs had grown from the original $10.6 billion baseline to $16.5 billion by 2021, and the latest $6 billion-plus increase was flagged in a report this September.
What is Block 4?
Block 4 is a major modernization package for the F-35 fleet, adding advanced weapons, sensors, and electronic warfare capabilities. It was originally envisaged to transform the F-35 into a more lethal and survivable multirole fighter, with full integration of the latest munitions and enhanced onboard systems. The suite was meant to put the F-35 on par with current-generation fighter aircraft in key mission areas.
Why is Block 4 slipping?
Block 4's completion has now slipped to 2031 at the earliest, a delay of at least five years. The primary cause is the Technology Refresh 3 (TR-3) package, an extensive hardware and software upgrade needed to enable Block 4's new capabilities. TR-3, valued at $1.9 billion, has run into significant technical challenges and schedule pressure.
TR-3's problems have had a cascading impact. It enables a suite of engine, power, and thermal management upgrades the F-35 needs to handle Block 4's increased electrical and cooling load. But the Pratt & Whitney F135 engine upgrade, a core part of that, hasn't even begun production yet, with the GAO saying it won't be until 2031. That means capabilities dependent on the updated engine have been deferred to at least 2033.
The GAO found that in 2024, Lockheed Martin delivered 110 F-35s, but all of them were late by an average of 238 days. That delivery slate was already crowded with the existing fleet, and the delays have added further pressure. With the current production flow, there isn't enough capacity to add Block 4 upgrades.
| Sept 2021 | Sept 2025 | Sept 2028 | Sept 2031 | Sept 2033 |
|---|---|---|---|---|
| Baseline cost: $10.6B | New cost estimate due | $16.5B | $16.5-B | $16.5-$22.5B |
| Full Block 4 | TR-3 risk reduction | TR-3 production | Block 4 rollout | Block 4 complete |
What is changing now?
The Pentagon has decided to reduce the scope of Block 4, aiming to deliver fewer capabilities by 2031 at a more predictable pace. As outlined here, this adjustment should allow the program to get back on track. Consequently, some elements of Block 4's original vision will be deferred or removed entirely.
The GAO said the Pentagon has not provided a detailed breakdown of the at-least-$6-billion cost increase for Block 4. The department has said the restructured program will have fewer capabilities and unknown costs until the new estimate is complete, expected later in 2025. Some capabilities remain deferred, and others' timing is uncertain.
Congress directed the Defense Department in 2023 to manage Block 4 and TR-3 as a subprogram with improved oversight. That was in response to concerns about cost growth and schedule delays. The Pentagon's broader F-35 program estimate was raised to $536.2 billion, up $51 billion from the previous 2023 assessment, though that figure includes the F135 engine upgrade and sustainment of over 2,400 aircraft.
What comes next?
The Pentagon has awarded a $1.3 billion risk-reduction contract to Pratt & Whitney, but that is only an early step in an extensive process. The program expects to award an engine core upgrade development contract after the risk-reduction contract ends in 2026.
The broader F-35 program, including Block 4, the F135 engine upgrade, and sustainment, is projected to cost over $2 trillion across its 77-year life cycle. Even with the Block 4 delay, the Pentagon is committed to fielding a more capable aircraft as soon as possible. But the question remains: will those deferred capabilities be recovered, and if so, when? The answer will shape the F-35's future.